During the close-out procedures, what is NOT a role of the contractor?

  1. Providing a punch list

  2. Conducting the final walk through

  3. Submitting warranties and maintenance contracts

  4. Cleaning up construction debris

The correct answer is: Conducting the final walk through

The correct answer pertains to the roles during the close-out procedures, specifically highlighting that conducting the final walkthrough is typically the responsibility of the project owner or the owner's representative rather than the contractor. In a project close-out, the punch list is often generated by the contractor, identifying minor issues that need to be addressed before project completion. Submitting warranties and maintenance contracts is also part of the contractor's responsibilities, as they formalize the terms under which the owner receives guarantees about the work performed. Additionally, cleaning up construction debris falls under the contractor's obligations to ensure the site is left in an acceptable condition. Therefore, since the final walkthrough is generally led by the owner or their representative to ensure that the project meets the agreed-upon specifications and quality, this delineation clarifies the role of the contractor in this phase of the project.