Study for the California Supplemental Exam (CSE) with flashcards and multiple-choice questions. Each question includes hints and explanations to prepare you and enhance your understanding for the exam.

Practice this question and more.


Under the Permit Streamlining Act, how many days do public agencies have to notify an applicant if a project application is complete?

  1. 30 calendar days

  2. 60 calendar days

  3. 90 calendar days

  4. 180 calendar days

The correct answer is: 30 calendar days

The correct answer is that public agencies have 30 calendar days to notify an applicant if a project application is complete under the Permit Streamlining Act. This is significant as the Permit Streamlining Act was established to facilitate the processing of permits for development projects and help establish clear timelines for public agencies. By mandating a 30-day notification period, the Act aims to improve efficiency and reduce delays in the permitting process. This time frame allows applicants to understand the status of their applications quickly, enabling them to make informed decisions about potential next steps. Understanding this time frame is essential for both applicants and public agency staff to ensure compliance with the law and efficient project planning.