What time frame is set for the correction of work found not to comply with contract documents after substantial completion?

  1. 6 months

  2. 1 year

  3. 2 years

  4. 10 years

The correct answer is: 1 year

The correct time frame for the correction of work found not to comply with contract documents after substantial completion is one year. This period is established to ensure that any deficiencies or nonconforming work can be addressed adequately without extensive delays after the project has been completed. This one-year duration aligns with typical warranty periods in construction contracts, allowing the owner to identify issues related to workmanship or materials that may not have been apparent at the time of substantial completion. Although construction defects might have longer statutes of limitations or warranties under different laws, the one-year period specifically relates to the completion phase of a project and is commonly accepted in the industry. This timeframe provides a reasonable balance for both owners and contractors, giving the contractor the opportunity to remedy any issues while still ensuring that owners have recourse for defects discovered shortly after the work has been finalized.