Study for the California Supplemental Exam (CSE) with flashcards and multiple-choice questions. Each question includes hints and explanations to prepare you and enhance your understanding for the exam.

Practice this question and more.


Which of the following is a responsibility transferred to the construction manager?

  1. Preparation of construction change directives

  2. Approval of change orders

  3. Certification of applications for payment

  4. Design of the project scope

The correct answer is: Certification of applications for payment

The correct answer reflects a responsibility that can be reasonably transferred to the construction manager. Certification of applications for payment involves verifying that the work completed is in line with the project progress and adheres to the agreed terms. This function is critical within the construction management role, as it ensures that payment is only made for work that meets the established standards and agreements. Transferring this responsibility to the construction manager helps streamline the payment process, as they are often closely involved with the day-to-day operations of the project and have the necessary oversight to make informed decisions. This role provides a check in the process, ensuring that all work is correctly documented and accounted for before funds are released. In contrast, the preparation of construction change directives often involves complex discussions and negotiations regarding project changes and is typically managed by the project owner or architect. Approval of change orders is similarly a significant responsibility that usually remains with the owner or their designated representatives, as this involves financial implications tied directly to project budgets. The design of the project scope fundamentally falls under the domain of the architect or designer, who establishes the overall vision and requirements of the project, rather than the construction manager.